Ref
 
Item
Due/Explanation
Resource
1.
 
CPA certification of financial management adequacy.
30 days after signing the financial assistance award.
See your cooperator-specific special award conditions posted on
Quarterly financial reports
2.
 
Projection of advances and reimbursements.
3.
 
Performance report, quarterly: Reporting progress on ITA measures (Part A).

 

30 days after the end of each quarter.

 

 

Docs icon
4.
 
Performance report, quarterly: Reporting progress on cooperator measures (Part B).
Docs icon
5.
 
Performance report calendar: Quarterly updates (Part C).
Docs icon
6.
 
Financial report SF-425, quarterly
Quarterly financial reports
7.
 
Success agreement.
Several weeks prior to the first activity where individual companies are recruited to participate.
Trade.gov/mdcp web address
8.
 
Send list of participating companies to ITA members of your federal team.
Local ITA offices (USEACs) can establish good rapport, provide advice and support, and improve your ability to get companies to report export successes.
9.
 
Success stories.
As often as you can.
Trade.gov/mdcp web address
10.
 
Fiscal year operating plan.
Mid-August.
Trade.gov/mdcp web address
11.
 
Budget modifications. (Where cumulative transfers between the 8 standard OMB budget categories exceed 10% of the total project budget.)
Request Grants Officer approval as soon as possible.
Quarterly financial reports
12.
 
Budget modifications. (Where cumulative transfers between the 8 standard OMB budget categories are less than 10% of the total project budget.)
Grants Officer approval is NOT required.
Coordinate with your ITA-led federal team.
13.
 
Fly America Act waiver requests.
Three (3) weeks prior to proposed travel on non-U.S. flagged carrier.
Guidelines for submitting waiver request: Trade.gov/mdcp web address
14.
 
Requests to extend award period.
As soon as possible. Not later than 30 days prior to the end of the award period.
Quarterly financial reports
15.
 
Requests to change key project personnel.
Quarterly financial reports
16.
 
Requests to change scope of project.
Quarterly financial reports
17.
 
Performance report, final.
Not later than 90 days after the end of the award period.
18.
 
Financial report, final.
Quarterly financial reports

 